Parking Lot Update

parking lot repair

The council has approved a plan to repair parts of the parking lot this summer.  Repairs for this summer include replacing the remainder of the road between the two parking lots, replacing a large area in the south parking lot, and crack sealing most of the larger cracks in both parking lot.  The council authorized the $30,000 needed for this work. 

The crack sealing will be done during the first part of the summer, but the asphalt repair will not start until after August 1, because of the availability of the contractor doing the work.  Next year, some additional crack sealing will be planned,  then chip coating and sealing the entire parking lot, and painting parking spaces.

parking lot repair